Scheduled Maintenance - Coventry Datacentre - Fibre Wavelength Services

Scheduled Maintenance Report for UK Servers Status

Completed

The scheduled maintenance has been completed.
Posted Jul 24, 2024 - 05:00 BST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 23, 2024 - 23:00 BST

Scheduled

During the above period one of the suppliers of wavelength services providing connectivity from our Manchester PoPs to our Coventry datacentres will be carrying out essential maintenance work.

Colt intends to carry out internal maintenance within its network. This has been designated as ESSENTIAL. The nature of this work is to perform a network circuit re-route.
Work is required to perform infrastructure maintenance to ensure the continued integrity of the network.

Due to the redundant nature of the UK Servers network this maintenance is not expected to be service affecting for our customers as traffic will automatically re-route on alternative paths however due to the nature of the work the network to our Coventry site should be deemed at risk during this period.

Whilst a lengthy maintenance window is scheduled to cover all eventualities the service provider does not expect the circuits to be offline for the duration of the maintenance window and UK Servers customer's services should not be affected.
Posted Jun 18, 2024 - 14:26 BST
This scheduled maintenance affected: Coventry - Continuity House (205/DC3), Coventry (DH1), Coventry (DH2), and Equinix MA1 (MCR).