Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 06, 2024 - 22:00 GMT
Scheduled
During the above period one of the suppliers of wavelength services providing connectivity from our London PoPs to our Coventry datacentres will be carrying out essential maintenance work.
This work involves essential network maintenance activity taking place at one of NEOS sites where CPL Replacement - traffic migration is being completed to ensure consistency throughout the network, enhance functionality and prevent obsolescence.
Due to the redundant nature of the UK Servers network this maintenance is not expected to be service affecting for our customers as traffic will automatically re-route on alternative paths however due to the nature of the work the network to our Coventry site should be deemed at risk during this period.
Whilst a lengthy maintenance window is scheduled to cover all eventualities the service provider does not expect the circuits to be offline for the duration of the maintenance window and UK Servers customer's services should not be affected.
Posted Oct 04, 2024 - 14:32 BST
This scheduled maintenance affected: Coventry - Continuity House (205/DC3), Coventry (DH1), and Coventry (DH2).