Planned UPS Maintenance at our Coventry Facility - Data Hall 3 C Feeds Only - At Risk Period

Scheduled Maintenance Report for UK Servers Status

Completed

The scheduled maintenance has been completed.
Posted May 29, 2025 - 12:30 BST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 29, 2025 - 09:30 BST

Scheduled

During the above period we will be putting all UPS's at Coventry datacentres into maintenance bypass for a period of time in order to carry out firmware upgrades to these systems.

Due to the redundant nature of the UK Servers power supply services this maintenance is not expected to be service affecting, customer "A/B" rack power feeds will be unaffected by this maintenance

Whilst a lengthy maintenance window is scheduled to cover all eventualities the service provider does not expect primary UPS systems to be offline for the duration of the maintenance window and UK Servers customer's services should not be affected however due to the nature of the work the systems
Posted May 21, 2025 - 19:13 BST
This scheduled maintenance affected: Coventry - Continuity House (205/DC3).